BIM 360 to Autodesk Construction Cloud: what happens to old project data

By SourceX Editorial · Reviewed by Noah Loul ·

Short answer

Moving from BIM 360 to Autodesk Construction Cloud is a project-by-project decision, not a single switch. Firms choose which active projects move to ACC and must plan separately for closed projects, version history, markups, issues, RFIs and submittals. Confirm your account's dates and migration scope with Autodesk, then archive closed projects in formats your firm controls.

Key takeaways

  • Confirm the dates, migration path and scope that apply to your account with Autodesk or your reseller, in writing.
  • Move active and closeout projects; archive older closed projects in formats your firm controls.
  • Version history lives in issued sets, transmittals and logs as much as in file versions, so archive all of them.
  • RFI, submittal and issue logs need their responses and attachments, not only the log rows.
  • Client agreements decide what the firm may keep, reuse or license from each project.

What is changing, and what should firms confirm first?#

Autodesk is moving customers from BIM 360 to Autodesk Construction Cloud, its newer platform built around Autodesk Docs as the shared document environment. Timing, migration tools and continued BIM 360 access can vary by account and contract, so the first job is to confirm what applies to yours.

Ask Autodesk or your reseller, in writing, which dates apply, which projects the migration path covers, whether closed or archived projects are included, how version stacks and markups transfer and how long BIM 360 stays accessible afterward. Treat anything not confirmed as something your firm must export itself.

Autodesk's past retirements show why waiting is risky. Its BIM 360 Plan FAQ says customers can no longer access BIM 360 Plan project data once their contract ends and advises exporting plans and tasks before the term ends. BIM 360 Team and A360 Team files were first moved to read-only access, with options to copy them to Autodesk Docs or download them, and access was removed after those products were fully retired at the end of 2023.

This is a records decision as much as an IT one. The BIM manager knows how projects are structured; the managing principal and whoever handles risk management know which records the firm may need long after a building is occupied.

What to check for each kind of project content#

Each kind of project content raises its own question in the move, and the answer decides whether it can migrate or should be archived. Use the table as a review sheet on a pilot project before committing the whole portfolio.

What to check for each kind of project content
Project contentQuestion to answerHow to protect it
Current drawings and modelsDoes the latest version migrate with folder structure intact?Verify on a pilot project before bulk moves
Version historyDo earlier versions and their dates come across, or only the latest?Archive issued versions with dates in file names
Markups and commentsDo markups stay attached to the right version?Export marked-up sheets to PDF
IssuesDo status, assignees, comments and photos survive?Export issue logs with attachments
RFIs and submittalsDo responses, reviewers and attachments migrate with each item?Export logs and full item reports
Transmittals and packagesIs the record of what was sent, to whom and when, kept?Export transmittal logs
Permissions and membersDo roles map cleanly to ACC?Document roles before migrating
Closed projectsAre they in scope, or left behind in BIM 360?Archive outside Autodesk

Keeping version history when you archive#

Version history survives an archive when it preserves what was issued, when and to whom, rather than every intermediate save. For most firms, the issued sets, addenda, bulletins, transmittals and the revision narratives that explain them are the history that matters in a dispute.

  • Export each issued set as PDF, named with project number, set name and issue date.
  • Keep native files for current and issued versions: RVT, DWG and an IFC export for long-term readability.
  • Export transmittal and package logs showing recipients and dates.
  • Export RFI, submittal and issue logs with full item reports and attachments.
  • Write a manifest per project: what was exported, by whom, when and from which project.
  • Store archives in firm-controlled storage with read-only access by role.

Using Data Connector for structured project logs#

Autodesk's Data Connector is the route for getting issues, RFIs and other project records out as structured tables rather than PDFs. It delivers CSV files for each table, downloadable one table at a time or as a zip, and extractions can be scheduled daily, weekly or monthly.

Two details shape the plan. A project administrator can extract data only for the single project they are in, while members with executive overview access, granted by an account administrator, can extract across the whole account; for a portfolio archive, ask for executive overview access. Extracted files can be downloaded for up to 30 days after extraction, so save every run to firm storage straight away.

Keep the CSV tables beside the PDF item reports. The tables preserve IDs, dates and status changes that let you link an RFI to its sheet revision; the PDFs preserve what reviewers actually saw.

Which projects to move and which to archive#

Projects in design, construction administration or closeout usually move to ACC, because teams still work in them. Older closed projects are usually better archived, which keeps the new environment clean and avoids spending migration effort on projects nobody opens.

Set the archive period by risk, not habit. Professional liability exposure, statutes of repose, client contract retention clauses and insurer guidance all bear on how long project records must stay retrievable, and they differ by state and project. Ask your insurer and counsel, then write the rule into the firm's records policy.

A dispute changes the default. When a closed project has an open claim, preserve it exactly as it stands and let counsel decide how it is copied, because a migration or a fresh export can alter dates and metadata that matter as evidence.

Which projects to move and which to archive
Project statusDefaultException
In design or construction administrationMove to ACCNone; teams work in it daily
In closeout or warrantyMove to ACCArchive if the team works only from closeout documents
Closed, with an open claimPreserve as is and involve counselNo migration or re-export without legal advice
Closed, no open mattersArchive outside AutodeskMove if the client has a follow-on phase
Pursuits never awardedArchive or delete under policyKeep proposal content the firm reuses

Who owns the project records you archive?#

Ownership of project records depends on the owner-architect or owner-engineer agreement, and it is often split. Agreements based on common industry forms typically address instruments of service, licenses to the client and record copies. AIA B101, for instance, provides for the owner to pay the architect a licensing fee for continued use of the instruments of service after certain terminations, and the short-form B105-2017 grants the owner a limited license to use them only as a reference for maintaining, altering and adding to the project. Custom client agreements can go further and claim deliverables outright.

Internal records such as review comments, design team discussions and staffing notes are usually the firm's own, while drawings and models issued to the client may be licensed to or owned by the client. Consultants' files in a shared project belong to the consultants. Sort the archive along those lines so later reuse decisions are easier.

Illustrative: an engineering firm splits its BIM 360 portfolio#

Illustrative: a fictional structural and MEP engineering firm runs most of its projects in BIM 360. Planning the move to ACC, the BIM manager sorts every project into active, in closeout or closed.

Active and closeout projects migrate after a pilot confirms folder structure and version stacks. Closed projects are archived: issued sets as PDF, native models with IFC exports, RFI and submittal logs with responses, issue logs with photos and transmittal records, each with a manifest. Client deliverables and internal review records go into separate folders.

Later, a building owner raises a question about a connection detail on a closed project. The firm finds the RFI, the response, its date and the sheet revision in its own archive without reopening BIM 360.

Why RFI and review history deserves care#

RFI and review history records how engineers and architects reason through problems: the question from the field, the options considered, the response and its effect on the drawings. That sequence protects the firm in disputes, and it is the kind of professional workflow AI developers study when building tools for design and construction.

Any reuse outside the firm starts with client contracts and confidentiality. Records that belong to clients, identify their buildings or carry security-sensitive details are carved out before any assessment.

SourceX begins with a metadata-only fit check that describes which project records exist, how many years they cover and how RFIs, submittals and issues link to drawings and outcomes. No files leave the firm at that stage.

If a package proceeds, the SourceX five-step transaction applies: Supply, Rights, Preparation, Approval and Delivery. The Rights step separates firm-owned records from client deliverables, Preparation removes client, site and personal details, and the firm approves every release.

Frequently asked questions

Will ACC keep our BIM 360 project numbers and folder structure?

Confirm it on a pilot project before migrating the rest. Even when structure transfers cleanly, keep a crosswalk of old project names, IDs and folder paths so links in emails, reports and the archive still point to the right place.

Should we archive in native formats or PDF?

Both. PDF keeps issued sheets readable without Autodesk software. Native RVT and DWG files keep models reusable, and an IFC export, an open standard, adds a copy that does not depend on any single vendor's software.

What about cloud workshared Revit models?

Cloud workshared models need specific handling to produce standalone copies for an archive. Have the BIM manager document the steps, test them on one closed project and confirm the archived model opens without a connection to the original project.

Do consultants export their own files?

Usually, yes. Consultants own their work product and should archive it under their own policies. Your archive should keep what your firm received and relied on, with transmittals showing when it arrived.

Can old project records be licensed to AI developers?

Some can. Firm-owned records such as RFI reasoning and internal review comments may qualify once client contracts are reviewed and client, site and personal details are removed. Client deliverables are usually excluded unless the client agrees.

Sources

  • Autodesk's BIM 360 Plan FAQ says customers can no longer access BIM 360 Plan project data once their contract ends and advises exporting plans or tasks before the subscription term ends. Source
  • BIM 360 Team and A360 Team files were moved to read-only access with options to copy to Autodesk Docs or download, and the products were fully retired at the end of 2023, after which access was removed. Source
  • Data Connector delivers CSV files per table, can be scheduled daily, weekly or monthly, files can be downloaded for up to 30 days, and project administrators extract only their own project while executive overview members extract across the account. Source
  • AIA B101 provides for a licensing fee for the Owner's continued use of Instruments of Service after certain terminations, and B105-2017 grants a limited license to use them as a reference for maintaining, altering and adding to the Project. Source